车站技术作业基本图的自动生成

Automatic generation of basic diagram for railway station technical operation

  • 摘要: 采用模拟人工铺画的方法编制车站技术作业基本图,在满足全天调机使用效率最大化,列车到发技术作业时间约束和股道占用约束的前提下,连接调机和列车,再根据调机空闲情况进行调整,使生成的基本图更好地符合车站作业需求,能够高效地利用车站的各项资源,并大量降低了用户绘制图表的劳动强度。以南昌火车站和昆明东编组站为例,实现了客运站和大型编组站技术作业基本图的自动铺画,证明了该方法在工程应用方面的可行性。

     

    Abstract: The basic diagram for railway station technical operation was drawn by using the drawing method of artificial simulation. Under the premise of meeting the requirements of maximum of all day locomotive efficiency, as well as train arrival and departure technical operation time constraint and track occupancy constraint, the drawing system linked trains and locomotives. According to the idle condition of locomotives, the basic diagram was adjusted further to meet the needs of railway station operation. The use of drawing system could make efficient use of railway station resources, reduced the labor intensity of drawing diagram. Nanchang Railway Station and Kunming East Marshalling Yard were taken as examples to implement the automatic generation of basic diagram for railway station technical operation in passenger station and large marshalling yard. The feasibility of this method in engineering application was proved.

     

/

返回文章
返回